Abstract:
Based on the existing regional engineering geological survey data and according to the current national standard identification method of liquefaction in China,the liquefaction situation of the saturated sand layer,silty sand layer and silty soil layer at 20 m below the surface is checked and identified in order to find out the liquefaction
situation in some areas of Anqing. The project covers the Yixiu District,Yingjiang District,Daguan District and Huaining County of Anqing,with a total area of 820 square kilometers. The results show that 10 out of 27 engineering